Question
A manufacturing plant has a target for a -day period to produce an average of units per day. During the first half of the period, the plant averaged units per day. What must be the average daily production in the second half of the period to meet the overall target?

Answer Choices
- A.
- B.
- C.
- D.
- E.
Steps
| Explanation | Calculations | Help |
|---|---|---|
We name as the average units per day in the second half of the period. | ||
We calculate the total units required for the 30-day period. | ||
We find the units produced in the first 15 days. | ||
We determine how many units remain to meet the target. | ||
We express the remaining production as times 15 days. | ||
We solve for by dividing both sides by 15 and simplifying. | Theory & Tactics Method Card EQUA1-A Click to view full details Theory & Tactics Method Card FDPR2-A Click to view full details |
Scroll horizontally to view all columns
Final Answer
C
Question
A manufacturing plant has a target for a -day period to produce an average of units per day. During the first half of the period, the plant averaged units per day. What must be the average daily production in the second half of the period to meet the overall target?

Answer Choices
- A.
- B.
- C.
- D.
- E.
Steps
| Explanation | Calculations | Help |
|---|---|---|
We name as the average units per day in the second half of the period. | ||
We calculate the total units required for the 30-day period. | ||
We find the units produced in the first 15 days. | ||
We determine how many units remain to meet the target. | ||
We express the remaining production as times 15 days. | ||
We solve for by dividing both sides by 15 and simplifying. | Theory & Tactics Method Card EQUA1-A Click to view full details Theory & Tactics Method Card FDPR2-A Click to view full details |
Scroll horizontally to view all columns
Final Answer
C