Question
A software QA team is required to test an average of cases per day over a -day sprint. For the first days, the team averaged cases each day. How many cases per day must the team average over the remaining days to meet the overall requirement?

Answer Choices
- A.
- B.
- C.
- D.
- E.
Steps
| Explanation | Calculations | Help |
|---|---|---|
We name as the average number of cases per day over the remaining 18 days. | ||
We calculate the total number of cases required for the 30-day sprint. | ||
We calculate the number of cases already tested in the first 12 days. | ||
We find how many cases remain to be tested in the remaining days. | ||
We express the remaining cases as the product of the daily rate and the number of days left. | ||
We solve for by dividing both sides by 18 and simplifying the fraction. | Theory & Tactics Method Card FDPR2-A Click to view full details |
Scroll horizontally to view all columns
Final Answer
B
Question
A software QA team is required to test an average of cases per day over a -day sprint. For the first days, the team averaged cases each day. How many cases per day must the team average over the remaining days to meet the overall requirement?

Answer Choices
- A.
- B.
- C.
- D.
- E.
Steps
| Explanation | Calculations | Help |
|---|---|---|
We name as the average number of cases per day over the remaining 18 days. | ||
We calculate the total number of cases required for the 30-day sprint. | ||
We calculate the number of cases already tested in the first 12 days. | ||
We find how many cases remain to be tested in the remaining days. | ||
We express the remaining cases as the product of the daily rate and the number of days left. | ||
We solve for by dividing both sides by 18 and simplifying the fraction. | Theory & Tactics Method Card FDPR2-A Click to view full details |
Scroll horizontally to view all columns
Final Answer
B